ISL358U Project Management 2021-2022 Yaz Okulu Soruları
20 soru · Yaz okulu · 2021-2022
ISL358U Project Management dersinin 2021-2022 yaz okulu sınavı 20 sorudan oluşur; ders AÖF İşletme (İngilizce) bölümünde okutulur. Sorular aşağıda sırasıyla yer alır. Doğru cevaplar ve sonucun, testi çözdüğünde görünür.
Önizleme · 20 soru. Cevaplamak ve sonucunu görmek için sınavı başlat.
Sorular
20 soru
Soru 1
Soru 2
Soru 3
Soru 4
Soru 5
Soru 6
Soru 7
Soru 8
Soru 9
Soru 10
Soru 11
Soru 12
Soru 13
Soru 14
Soru 15
Soru 16
Soru 17
Soru 18
Soru 19
Soru 20
Sınav modunda süre tutulur, doğru cevaplar ve sonucun sınav bitince görünür.
Dersin üniteleri
ISL358U Project Management ders sayfası: bütün sınavlar ve üniteler
Soruların metni (otomatik okuma)
Görsellerden otomatik okunmuştur; hata içerebilir. Sorular, görsellerdeki hâliyle geçerlidir.
When a project continues from one phase to the next, the project management methodology helps the project manager to do several things. Which of the following is not one of them? A) to establish priorities B) to identify the required resources and costs C) to identify the required project tasks D) to plan and update schedules E) to measure customers' performance
Which of the following is not one of the project management process groups? A) Executing Process B) Closing Process C) Planning Process D) Manipulating Process E) Initiating Process
A classic project life cycle consists of four distinct phases. Which of the following is not one of those phases? A) performing B) initiation C) forming D) Dy Zlosúre E) planning
4. Which of the following does not exemplify a project? A) Creating a new yoga video on Youtube Designing a yacht according to a customer request C) Writing a scientific paper D) Establishing a production planning software Taking lecture notes
• This activity has zero slack. • If this activity is delayed, the project completion will be delayed. Which fundamental term is explained in the information given above? A) Parallel Activity et3. B) Critical Activity C) Dummy Activity D) Merge Activity E) Burst Activity
Which of the following can be described as "a visual representation of a project's activities and the preceding requirements for completing the project"? A) Predecessor activity B) Descendent activity C) Node D) Merge point E) Precedence diagram
Which of the following is true about CPM? A) CPM aims to develop a specific and optimal time-cost relationship. B) CPM is suitable for non-repetitive jobs. C) CPM has three duration estimations. D) CPM includes unpredictable activities. E) CPM time-related and not activity-oriented.
8. The PERT system relies on three estimates for each activity:,- And..... Which of the following best completes the sentence above in the correct order? A) an optimistic time, a probable time, a pessimistic time a maximum time, a minimum time, a pessimistic time C) an optimistic time, a highly probable time, a pessimistic time D) a maximum time, highly probable time, a minimum time E) a maximum time, a highly probable time, a pessimistic time
In RACI model, what does "R" stand for? A) Required B) Responsive C) Respectful D) Review E) Responsible
10. - makes it easy to plan, schedule and reschedule the resource needed especially for big projects. Which of the following completes the sentence above? A) Resource leveling b) Human resources management . Responsibility assignment matrix Resource management software E) Staffing management plan
Which of the following two-words are overlapping concepts, and often used interchangeably? A) Servant and owner B) E Project manager and leader C) Lecturer and pupil D) Producer and consumer E) Employer and employee
In which of the following stages of team development do group members begin to resist authority? A) Adjourning B) Forming C) Norming D) Storming E) Performing
1. Exchange of purpose II.. A right to say no III. Joint accountability IV. Extreme dishonesty »Which of the above are required to develop the idea of partnership between the project manager and the team? A) Al land ilr" B) II and C) I, Il and Ill D) 1, Ill and E) II, III, and
What is mainly aimed in exploiting strategy? A) To involve merging with a firm to increase the chances of securing gains and agreeing to share rewards B) To determine the time reserve C) To find the best way to take advantage of the opportunity by eliminating the uncertainty in the project D) To record when response plans are actually implemented and how much effort or cost occurs E) To execute agreed risk strategies
What is the name of the simulation which is a computerized technique that allows people to account for risk in quantitative analysis and decision making? A) Quantitative Risk Analysis B) Mitigation C) Performance Data D) Monte Carlo Analysis E) Decision Tree Analysis
Which of the below is used to determine the likelihood of a particular risk occurring in a project? A) Risk categorization B) Risk probability and impact assessment. C) Expert Judgement D) Risk data quality assessment E) Interpersonal and team skill
Let's assume that BAC=1200; EAC=1500 for a project. PCp=50% and PCa=75 %; ACWP= 1000 at the status date. What is BV value? A) - 300 B) 300 C) ∞• D) 250 E) 450
Let's assume that BCWP=820, ACWP= 1000 for. a project. What is CPI value? A) 0,82 B) 1 C) 0,62 D) 1,22 E) 1,32
In this activity, the team formally hands off the project deliverables to the new owner. This includes not only the possession of the item, but also the ability to support the item for long term. What is this topic area covered in the project checklist? A) Obtain client acceptance B) Transition deliverables to owner C) Document final project financials D) Update resource schedules E) Capture lessons learned
Which of them is not in the agenda of the post mortem meeting? A) Final step B) Summary information C) Problems and critical success factors D) Transfer of ground rules E) Recommendations for improvement