ISL358U Project Management 2021-2022 Vize Soruları
20 soru · Vize · 2021-2022
ISL358U Project Management dersinin 2021-2022 vize sınavı 20 sorudan oluşur; ders AÖF İşletme (İngilizce) bölümünde okutulur. Sorular aşağıda sırasıyla yer alır. Doğru cevaplar ve sonucun, testi çözdüğünde görünür.
Önizleme · 20 soru. Cevaplamak ve sonucunu görmek için sınavı başlat.
Sorular
20 soru
Soru 1
Soru 2
Soru 3
Soru 4
Soru 5
Soru 6
Soru 7
Soru 8
Soru 9
Soru 10
Soru 11
Soru 12
Soru 13
Soru 14
Soru 15
Soru 16
Soru 17
Soru 18
Soru 19
Soru 20
Sınav modunda süre tutulur, doğru cevaplar ve sonucun sınav bitince görünür.
Dersin üniteleri
ISL358U Project Management ders sayfası: bütün sınavlar ve üniteler
Soruların metni (otomatik okuma)
Görsellerden otomatik okunmuştur; hata içerebilir. Sorular, görsellerdeki hâliyle geçerlidir.
1. Which of the following is not one of the project management process groups?. A) Planning Process Closing Process Executing Process D) Manipulating Process E) Initiating Process
What is the purpose of project management? A) to integrate the components to accomplish the project goal B) to help companies grow in the field of technology C) to share common goals and resources D) to lead enterprises downsize E) to provide accreditation according to subjects
A classic project life cycle consists of four distinct phases. Which of the following is not one of those phases? A) initiation B) forming C) planning D) yerorming E) *E) closure
Which of the following is the essential benefit of implementing project management techniques? A) to control customer's needs B) to monitor the sales C) to implement projects D) to plan the budget E) to meet customers satisfactions
- process consists of tracking and reviewing the performance of the projects. Which of the following option fills in the blank above? A) Closing B) Initiating C) Monitoring and controlling D) Executing E) Planning
This is an activity that has more than one activity immediately preceding it. It has more than one dependency arrow flowing to it. • More than one activity must be completed before it can begin. Which fundamental term is explained in the information given above? A) Critical Activity B) Dummy Activity C) Parallel Activity D) Burst Activity E) Merge Activity
Activity Description Preceding Activity Activitiy Time To present None 10 the idea to the top management Preparing the 25 details ofthe service Traffic jam 20 stufy reports Cargo driver 15 reports Confirmatioan B, D 15 from Branch Offices Commission B, C, D 10 confimation According to the project activities above; what is the ES (early start time) for activity A? A) B) 5 ć) 10 D) 15 E) 20
Which of the following is false about work packages? A) Each work package should have its own outcome. B) Only one person should be directly: answerable for the work package. C) They can be considered miniature projects. D) One work package may summanze or pose modity another. E) They may include several milestones.
Which of the following does not exemplify a project? A) Writing a scientific paper B) Taking lecture notes C) Designing a yacht according to a customer request D) Creating a new yoga video on Youtube E) Establishing a production planning software
I. Project objective II. Deliverables III. Milestones Which of the elements given is / are included in the definition of the project scope? """. A) Only l .. B) Only C) I and D) Il and I!! E) I, Il and, III
11. A node in the AON system or an arrow in the AOA system represents _ Which of the i below beşt cómpletes the sentence above in the correct order? 1 A) an activity B) an undertaking c) aplan D) a forecast ' E) an estimate
Which of the following is true about PERT? A) Time and cost are dependent in PERT. B) PERT has five duration estimations C) Uncertainty is not allowed with the estimates in PERT. D) PERT is oriented towards events. E) The activity duration is precise and definite in PERT.
Which of the following is true about CPM? A) CPM time-related and not activity-onented. B) CPM aims to develop a specific and optimal time-cost relationship. C) CPM has three duration estimations. D) CPM includes unpredictable activities. E) CPM is suitable for non-repetitive jobs.
Which of the below is true about AOA networks? A) It is not required to assign a distinctive number such as i and j to activities. B) It is convenient to use back arrows when necessary. C) The nodes denote the start and end of an activity in AOA technique. D) Use of dummy activities on the diagram should be avoided as it may cause confusion. E) Even if an activity relies on another, one arrow is enough on the network diagram.
a+4m+b 6 What does "a" refer to in the formula above? A) The mean duration of the activity B) The variance of the duration of the activity C) The pessimistic performance time D) The most likely time E) The optimistic performance time
When evaluating resource management software, under which criteria are features such as skills andforecasting included? A) User Interface B) Usability C) Scheduling and allocation tools D) Features and functionality E) Skíl's tracking
Which of the following is not one of the steps of successful resource management process? A) Searching for the resources B) Applying resource aggregation, leveling, and smoothing techniques C) Classifying the resources D) Estimating the required quantity of each resource E) Determining the necessary resources
Which of the following is not one of the things that a good staffing management plan includes? A) Training B) Staff assignments C) High salary ... D) Reassignment parts E) Staffing requirements
Which of the following is one of the challenges that a project manager must be aware of inrelation to resource allocation? A) Transparency building B) 'B) Availability of procedures C) Client changes D) Profitability activities E) Chánges in culture
Alan - resource management can easily affect the quality and the performance requirement of the project. Which of the following completes the sentence above? A) uncountable B) ineffective C) Important D) estimate E) measurable