20 soru
Soru 1
Soru 2
Soru 3
Soru 4
Soru 5
Soru 6
Soru 7
Soru 8
Soru 9
Soru 10
Soru 11
Soru 12
Soru 13
Soru 14
Soru 15
Soru 16
Soru 17
Soru 18
Soru 19
Soru 20
Sınav modunda süre tutulur, doğru cevaplar ve sonucun sınav bitince görünür.
Dersin üniteleri
ISL358U Project Management ders sayfası: bütün sınavlar ve üniteler
Soruların metni (otomatik okuma)
Görsellerden otomatik okunmuştur; hata içerebilir. Sorular, görsellerdeki hâliyle geçerlidir.
Which of the following statements about the fundamental attributes of a project is not true? A) A project states certain specific objectives B) Projects are temporary activities C) A project may be unique or have some unique elements D) A project plans neither schedule nor cost E) A project uses various resources to conduct project activities
Which of the following is the process group whose outputs are developing a project charter and identifying stakeholders? A) Executing process group B) Initiating process group C) Closing process group D) Monitoring process group E) Planning process group
. A significiant point or event in the project. • A significiant point with zero duration that indicates a cumulative sequence of events while performing the project.E" • An important achievement in a project. Which of the following is defined with the given phrases? A) Limits and Exclusions B) Technical Requirements C) Milestone D) Project Objective E) Denverables
-- are performed when one tries to define a logical dependency although the activities are not on the same path; one activity cannot begin after the other one is accomplished. Which of the following defines the concept given above? A) Critical activities B) Dummy activities C) Merge activities D) Parallel activities E) Burst activities
Which of the following can be described as "a visual representation of a project's activities and the preceding requitements for completing the project™? A) Node ('." B) Merge point 2. C) Precedence diagram D) Predecessor activity E) Descendent activity
6. Which of the following is not one of the approaches to determine the duration estimates necessary for PERT? Estimates derived from historical data NE) Estimates provided by the results. of simulation scenarios C) Timing in customer services after sales D) Predictions providęd by an experienced it Custon E) Customer requirements
Which of the following is the first step of resource management that aim to identify the types, amount, and characteristics of the resources needed? A) Resource forecasting B) Estimating resources C) Resource leveling D) Resource allocation E) Resource aggregations
Which of the following is not a benefit of the successful resource management applications? A) Building transparency B) Providing a safety net and projection C) Avoiding unexpected delays D) Preventing overloads and fatigue E) Decreasing efficiency
In which of the following stages of team development do group members begin to resist authority? A) Adjourning B) Performing C) Norming D) Storming E) Forming
Which of the following is not true about leaders? A) They count on impact. B) They play an administrative role. C) They consider interpersonal relations. D) They use emotional intelligence. E) They cope with change.
Which of the following can not be listed among the attributes of the effective project manager? "" › A) Proficient technical skits* B) Negotiating skills C) Powerful communication skills D) Perfect visionary E) Limited access
Which of the following is not included in Step Guides to Risk Management? A) Risk identification B) Risk analysis C) Prioritization of risks D) Risk assignment E) Exploiting risks
SWOT stands for --. Which of the following completes the sentence above correctly? A) Strengths, Weaknesses, Opportunities and Threats B) Strengths, Weaknesses, Optimization and Threats C) Sources, Weaknesses, Opportunities and Threats D) Strengths, Wellness, Optimization and Thoughts E) Strengths, Weaknesses, Opportunities and Thoughts
Which of the following is true in terms of risk monitoring? A) At regular status meetings, discussing risks should not always be an agenda item. B) Identifying and analyzing the emerging risks are not a part of monitoring, but a part of planning process: C) Project managers need to monitor risks at the end of the project. D) " D) Monitoring may indicate that the plannied response to risk is ineffective. E) The project manager should not consider the impact thresholds for the risks.
Which of the following is not a setup cost? A) Cost of warming a machine B) Amortization cost C) Cost of machine D) Transportation cost E) Cost of cooling a machine
Which of the following three metrics define the size of a project? A) Workload, Budget and PCT B) Man-hour, PCT and Earned Value C) Actual Cost, Planned Value and PCT D) PCT, Budget and Earned Value E) PCT, Earned Value and Actual Cost
17. What does "tardiness" mean in terms of projects? A) Delay Performance Monitoring D) Success E) Tracking
1. Project Closure Calendars II. Project Closure Resources III. Project Closure Communication Plan Which of the above is/are included in a project closing plan? ..!" A) Only B) land C) 1 and 1ll D) Il and III E) I, Il and I|l
The project management plan includes sub-plans. Which of the following can not be listed among these sub-plans? A) Leisure B) Procurement C) Schedule D) Scope E) Communication
1. Learning from mistakes II. Transferring what is learnt to the next projects Ili. Decrease the success probability of future projects Which of the statements) above wistare among the benefits of a postmortem revlew? A) Only B) I and C) I and ill D) I and I!! E) I, Il and Ill