ISL358U Project Management 2023-2024 Yaz Okulu Soruları

20 soru · Yaz okulu · 2023-2024

ISL358U Project Management dersinin 2023-2024 yaz okulu sınavı 20 sorudan oluşur; ders AÖF İşletme (İngilizce) bölümünde okutulur. Sorular aşağıda sırasıyla yer alır. Doğru cevaplar ve sonucun, testi çözdüğünde görünür.

Önizleme · 20 soru. Cevaplamak ve sonucunu görmek için sınavı başlat.

Sorular

20 soru

  1. Soru 1

    Which process group of project management process involves detalling the project scope, time frames, resources, and risks?
  2. Soru 2

    A major part of the project occurs in ---- phase.
  3. Soru 3

    In AOA diagrams, which of the following depicts the precedence relationships and it behaves as a link, but it is not a "real" activity, so it does…
  4. Soru 4

    • It is a significant point or event in the project • It symbolizes an important achievement in a project • Task association is the major…
  5. Soru 5

    "To describe a project, three kinds of data are required." Which of the following states these 3 kinds of data correctly?
  6. Soru 6

    Which of the following is the first step in PERT analysis?
  7. Soru 7

    is the pre-planning, scheduling and resource allocation method for maximizing the effectiveness.
  8. Soru 8

    Which of the following key responsibility is the same in RACI, PARIS and RASCI models?
  9. Soru 9

    Which of the following is not one of the five techniques and tools to estimate the resources for each activity in the project schedule?
  10. Soru 10

    Parker (2008) indicated four styles of team members where each contributed in different ways to the success of the team.
  11. Soru 11

    Which of the following can not be listed among the attributes of the effective project manager?
  12. Soru 12

    In which of the following stages of team development do group members agree on operating procedures and seek to work together?
  13. Soru 13

    — focuses on product- related risks such as scope, functionality and quality comparing actual and planned technical achievements.
  14. Soru 14

    Which of the following provides explanation of how you plan to implement the project risk management plan?
  15. Soru 15

    What is the name of the analysis technique used to determine which variables in system affect the system more?
  16. Soru 16

    "... is a master plan, which has been executed at the end of the planning phase of a project." Which of the following completes the sentence above…
  17. Soru 17

    Which of the following is not one of the steps you should follow in order to evaluate and control a project?
  18. Soru 18

    Review that all contractual requirements have been met.
  19. Soru 19

    Project Closure Calendars II.
  20. Soru 20

    Which of the following is not related to the postmortem review?

Sınav modunda süre tutulur, doğru cevaplar ve sonucun sınav bitince görünür.

Bu dersin diğer sınavları

Öğretim yılına ve döneme göre

Dersin üniteleri

ISL358U Project Management ders sayfası: bütün sınavlar ve üniteler

Soruların metni (otomatik okuma)

Görsellerden otomatik okunmuştur; hata içerebilir. Sorular, görsellerdeki hâliyle geçerlidir.

  1. Soru 1

    Which process group of project management process involves detalling the project scope, time frames, resources, and risks? A) Planning Process Group B) Monitoring Process Group C) Initiating Process Group D) Executing Process Group E) Controlling Process Group

  2. Soru 2

    A major part of the project occurs in ---- phase. This phase of project life cycle includes the stages of design, production and implementation. Which of the following completes the sentence above correctly? A) closure B) monitoring C) planning D) performing E) initiation

  3. Soru 3

    In AOA diagrams, which of the following depicts the precedence relationships and it behaves as a link, but it is not a "real" activity, so it does not have time duration? A) A network B) A milestone C) A dummy açtivity j.° D) A fask E) A node

  4. Soru 4

    • It is a significant point or event in the project • It symbolizes an important achievement in a project • Task association is the major characteristic of Which element of Project Scope is explaned in the information given above? A) Limits and exclusions B) Technical requirements C) Deliverables D) Project objective E) Milestone

  5. Soru 5

    5. "To describe a project, three kinds of data are required." Which of the following states these 3 kinds of data correctly? A) Activity information, precedence relationships, staff quality B) Activity information, budget, time information Activity information, precedence relationships, time information D) Staff quality, budget, time information E) Location, precedence »elationships, time information

  6. Soru 6

    6. Which of the following is the first step in PERT analysis? A) Calculating the expected project duration, Tx. . v.B) Calculating the expected value for each. activity by using a,m, and b. C) Determining three estimates; optimistic "a" modal "m", and pessimistic "b" durations for each activity. Calculating the variance of the project as the sum of individuat variance of activities on the critical path. E) Calculating the variance "s?* for each ' activity.

  7. Soru 7

    is the pre-planning, scheduling and resource allocation method for maximizing the effectiveness. Which of the following completes the sentence above correctly? A) Project management B) Time management C) Budget management D) Staff management E) Resource management

  8. Soru 8

    Which of the following key responsibility is the same in RACI, PARIS and RASCI models? A) Responsible B) Accountable C) Consulted D) Informed E) Support

  9. Soru 9

    Which of the following is not one of the five techniques and tools to estimate the resources for each activity in the project schedule? A) Project management software B) Expert judgment C) Follow-up estimating D) Alterative analysis E) Published estimating data

  10. Soru 10

    Parker (2008) indicated four styles of team members where each contributed in different ways to the success of the team. Which one is not a team member style according to Parker's study? A) Contributor B) Collaborator C) Communicator D) Challenger E) Changer

  11. Soru 11

    Which of the following can not be listed among the attributes of the effective project manager? A) Powerful communication skills B) Proficient technical skills C) Perfect visionary, D) Limited access E) Negotiating skills

  12. Soru 12

    In which of the following stages of team development do group members agree on operating procedures and seek to work together? A) Norming B) Adjouring C) Performing D) Storming E) Forming

  13. Soru 13

    — focuses on product- related risks such as scope, functionality and quality comparing actual and planned technical achievements. Which option best completes the sentence above? A) Reserve analysis B) Technical performance analysis C) Risk analysis D) Risk assignment E) Acceptance

  14. Soru 14

    Which of the following provides explanation of how you plan to implement the project risk management plan? A) Project risk management methodology B) • B) Risk report format C) Stakeholder based risks D) Risk categories E) Project risk manager

  15. Soru 15

    What is the name of the analysis technique used to determine which variables in system affect the system more? A) Assumption Analysis B) Decision Tree Analysis C) Monte Carlo Simulation D) Risk Probability and Impact Assessment E) Sensitivity Analysis

  16. Soru 16

    "... is a master plan, which has been executed at the end of the planning phase of a project." Which of the following completes the sentence above correctly? A) Correction plan B) Baseline plan. C) Executive plan D) Projection plan E) Financial plan

  17. Soru 17

    Which of the following is not one of the steps you should follow in order to evaluate and control a project? A) Measuring progress and performance B) Taking action C) Setting a baseline plan D) Postponing some non-urgent evaluation schedule E) Comparing plan with the actual

  18. Soru 18

    1. Review that all contractual requirements have been met. I!. Define the list of stakeholders related to new environment. III. Leave the problems behind and move on to the next project. Which of the statement above is/are among the project closing activities? A) Only ! B) land C) I and ill 1yd. D) I and Ill E) I, ll and I|l

  19. Soru 19

    1. Project Closure Calendars II. Project Closure Resources III. Project Closure Communication Plan Which of the above is/are included in a project closing plan? A) Only B) land C) 1 and Ill D) Il and !!! E) I, Il and I|l

  20. Soru 20

    Which of the following is not related to the postmortem review? A) Informing about the upcoming projects B) Organizing a meeting between the project team and key stakeholders. C) Collecting feedback from the operation teams D) Collecting feedback from the project E) Reporting the results of the meeting