İçeriğe geç

ISL358U Project Management 2023-2024 Vize Soruları

20 soru · Vize · 2023-2024

ISL358U Project Management dersinin 2023-2024 vize sınavı 20 sorudan oluşur; ders AÖF İşletme (İngilizce) bölümünde okutulur. Sorular aşağıda sırasıyla yer alır. Doğru cevaplar ve sonucun, testi çözdüğünde görünür.

Önizleme · 20 soru. Cevaplamak ve sonucunu görmek için sınavı başlat.

Sorular

20 soru

  1. Soru 1

    At which stage of the project management process "reporting performance" Included?
  2. Soru 2

    Which of the following can not be listed among the reasons why the Importance of project management increases?
  3. Soru 3

    In which process group stage is the project manager assigned to the project?
  4. Soru 4

    Which of the following statements about the fundamental attributes of a project js not true?
  5. Soru 5

    Which of the following is not among the phases of project life cycle?
  6. Soru 6

    It has more than one activity immediately following it.
  7. Soru 7

    Which of the following terms defines the expected results over the course, of the project?
  8. Soru 8

    - are performed when one tries to define a logical dependency although the activities are not on the same path; one activity cannot begin after the…
  9. Soru 9

    Which step can not be listed as a work to be done to review each package in the Work Breakdown Structure?
  10. Soru 10

    Which of the following can be listed among projects?
  11. Soru 11

    Which of the following is not one of the approaches to determine the duration estimates necessary for PERT?.
  12. Soru 12

    The PERT system relies on three estimates for each activity.
  13. Soru 13

    — is also often pointed as activity planning.
  14. Soru 14

    a + 4m+b 6 What does "a" refer to in the formula above?
  15. Soru 15

    Which of the following can be described as "a visual representation of a projects activities and the preceding requirements for complețing the…
  16. Soru 16

    - is the process of estimating the resource requirements of a company in a large timescale.
  17. Soru 17

    Which of the following is not among the benefits of the successful resource management applications?
  18. Soru 18

    Which of the following is the first step of resource management that aim to idențify the types, amount and characteristics of the resources needed?
  19. Soru 19

    Which of the following can be used to illustrate the number of required resources for a project throughout the project life cycle?
  20. Soru 20

    Which of the following is not among the 4 "M's of resource management?

Sınav modunda süre tutulur, doğru cevaplar ve sonucun sınav bitince görünür.

Bu dersin diğer sınavları

Öğretim yılına ve döneme göre

Dersin üniteleri

ISL358U Project Management ders sayfası: bütün sınavlar ve üniteler

Soruların metni (otomatik okuma)

Görsellerden otomatik okunmuştur; hata içerebilir. Sorular, görsellerdeki hâliyle geçerlidir.

  1. Soru 1

    At which stage of the project management process "reporting performance" Included? A) Closing process B) Monitoring and controlling process C) Executing process D) Planning process E) Initiating process

  2. Soru 2

    Which of the following can not be listed among the reasons why the Importance of project management increases? A) Increased customer focus B) Compression of the product life cycle C) Knowledge explosion D) Global competition E) Increase the number of managers

  3. Soru 3

    In which process group stage is the project manager assigned to the project? A) Initiating process B) Planning process C) Closing process D) Executing process r. E) Monitoring and controlling process

  4. Soru 4

    4. Which of the following statements about the fundamental attributes of a project js not true? A) A project plans neitter schedule nor cost "'BY A project states certain specific objectives A project uses various resources to conduct project activities D) Projects are temporary activities E) A project may be unique or have some unique elements

  5. Soru 5

    5. Which of the following is not among the phases of project life cycle? Performing Phase Planning Phase C) Initiation Phase D) Closure Phase E) Discussion Phase

  6. Soru 6

    It has more than one activity immediately following it. • It has more than one dependency arrow flowing from it. Which fundamental term is explained in the information given above? A) Burst Activity B) Critical Activity C) Merge Activity D) Dummy Activity E) Parallel Activity

  7. Soru 7

    Which of the following terms defines the expected results over the course, of the project? A) Artask B) 'A project objective C) A deliverable D) A technical requirement E) A limit

  8. Soru 8

    - are performed when one tries to define a logical dependency although the activities are not on the same path; one activity cannot begin after the other one is accomplished. Which of the following defines the concept given above? A) Parallel activities B) Burst activities C) Dummy activities D) Critical activities E) Merge activities

  9. Soru 9

    Which step can not be listed as a work to be done to review each package in the Work Breakdown Structure? A) Defines work (what) B) Identifies resources needed to complete a work package (how much) C) Identifies time to complete a work package (how long) D) Identifies a time-phased budget to complete a work package (cost) E) Identifies the number of social media followers (how popular)

  10. Soru 10

    10. Which of the following can be listed among projects? A) Practicing yoga poses Designing a yacht according to a customer request C) Routing manufacture of some yacht models D) Giving an answer to a supplier E) Taking lecture notes

  11. Soru 11

    11. Which of the following is not one of the approaches to determine the duration estimates necessary for PERT?. A) Predictions provided by an experienced person Estimates derived from historical data C) Estimates provided by the results of simulation scenarios D) TIming in customer services after sales E) Customer requirements

  12. Soru 12

    The PERT system relies on three estimates for each activity. Which of the following states these estimates correctly? A) An overrated calculation, a highly probable (modal) time and a pessimistic time B) An optimistic (minimum) time, a personal time and a pessimistic time C) An optimistic (minimum) time, a highly probable (modal) time and a pessimistic time D) Ant optimistic (minimum) time, a highly • - Probable (modal) time and an imaginary E) A personal time, a teamwork time and a management time

  13. Soru 13

    — is also often pointed as activity planning. This involves identifying the specific project activities. Which of the following complete the sentence above correctly? A) Network scheduling B) Network planning C) Network control D) Network making E) Network dissemination

  14. Soru 14

    a + 4m+b 6 What does "a" refer to in the formula above? A) The mean duration of the activity B) The most likely time C) The pessimistic performance time D) The optimistic performance time E) The variance of the duration of the activity

  15. Soru 15

    15. Which of the following can be described as "a visual representation of a projects activities and the preceding requirements for complețing the project"? (A) • Descendent activity B) Node c) Predecessor activity D) Precedence diagram" Ey • Merge point

  16. Soru 16

    - is the process of estimating the resource requirements of a company in a large timescale. Which of the following complete the sentence above correctly? A) Resource forecasting B) Resource assignment C) Resource budgeting D) Resource challanges E) Resource transfer

  17. Soru 17

    Which of the following is not among the benefits of the successful resource management applications? A) Providing a safety net and projection B) Measuring efficiency C) Avoiding unexpected delays D) Building privacy E) Preventing overloads and fatigue

  18. Soru 18

    Which of the following is the first step of resource management that aim to idențify the types, amount and characteristics of the resources needed? A) Resource leveling B) Resource forecasting C) Resource allocation D) Resource aggregations E) Estimating resources

  19. Soru 19

    Which of the following can be used to illustrate the number of required resources for a project throughout the project life cycle? A) Cumulative diagram B) Resource histogram C) Management Plan D) APM E) Horizontal bar chart

  20. Soru 20

    Which of the following is not among the 4 "M's of resource management? A) Manpower B) Money C) Mindset D) Material E) Machine