ISL358U Project Management 2023-2024 Final Soruları

20 soru · Final · 2023-2024

ISL358U Project Management dersinin 2023-2024 final sınavı 20 sorudan oluşur; ders AÖF İşletme (İngilizce) bölümünde okutulur. Sorular aşağıda sırasıyla yer alır. Doğru cevaplar ve sonucun, testi çözdüğünde görünür.

Önizleme · 20 soru. Cevaplamak ve sonucunu görmek için sınavı başlat.

Sorular

20 soru

  1. Soru 1

    At which stage of the project management process Is a large portion of the budget expanded?
  2. Soru 2

    • A significiant point or event in the project.
  3. Soru 3

    I. The dummy activities in both AOA and .
  4. Soru 4

    Which of the following is a step of resource management in which, we sum the resources that are required to complete all the activities with respect…
  5. Soru 5

    They are organized, passionate and goal-oriented who understand what projects have in common, and their strategic role in how organizations succeed,…
  6. Soru 6

    Which of the following is not listed among the the dures of the projet team markers?
  7. Soru 7

    Which of the following is among the internal stakeholders of a project?
  8. Soru 8

    I. Exchange of purpose II.
  9. Soru 9

    Which of the followings defines The Project Risk Management Methodology?
  10. Soru 10

    Which of the following is not among the strategies that can be used to avoid risk?
  11. Soru 11

    Which of the following is not a component of SWOT analysis?
  12. Soru 12

    Which of the below is used to determine the likelihood of a particular risk occurring in a project?
  13. Soru 13

    " is calculated as multiplying workforce by duration." What is the correct term to fill in the blank?
  14. Soru 14

    What is the evaluating date of a project?
  15. Soru 15

    , -_ is the difference between the latest finish late of the last activity and the earliest start date or the first activity of a projeci Which of…
  16. Soru 16

    There are two basic indicators to evaluate a project in terms of cost and workload.
  17. Soru 17

    Which of the following sub-plans is included in the projest management plan, not
  18. Soru 18

    Which of the following is not among the project life cycle?
  19. Soru 19

    Which of the following can not be said about the Postmortem Review?
  20. Soru 20

    A project closing plan should include the some sectlons.

Sınav modunda süre tutulur, doğru cevaplar ve sonucun sınav bitince görünür.

Bu dersin diğer sınavları

Öğretim yılına ve döneme göre

Dersin üniteleri

ISL358U Project Management ders sayfası: bütün sınavlar ve üniteler

Soruların metni (otomatik okuma)

Görsellerden otomatik okunmuştur; hata içerebilir. Sorular, görsellerdeki hâliyle geçerlidir.

  1. Soru 1

    At which stage of the project management process Is a large portion of the budget expanded? A) Executing process B) Planning process C) Initiating process D) Closing process E) Monitoring and controlling process

  2. Soru 2

    • A significiant point or event in the project. • A significiant point with zero duration that indicates a cumulative sequence of events while pertorming the project. • An important achievement in a project. Which of the following is defined with the given phrases? A) Deliverables B) Milestone C) Limits and Exclusions D) Project Objective E) Technical Requirements

  3. Soru 3

    I. The dummy activities in both AOA and . AON representation are necessary. - I1. It is easier to draw ande read AOA compared to AON. HI. AON allows representation of more relationships than AOA. v. ADA, activity can only begin once all have been completer 1 Predecessors Which of the above are true about ADA and AON? A) I and B) Jana!!! C) I| and Ill D) Il and E) Ill and

  4. Soru 4

    Which of the following is a step of resource management in which, we sum the resources that are required to complete all the activities with respect to the resource allocation step outputs? A) Resource allocation B) Estimating resource C) Resource leveling D) Resource forecasting E) Resource aggregations

  5. Soru 5

    They are organized, passionate and goal-oriented who understand what projects have in common, and their strategic role in how organizations succeed, learn and change" Who does this definition refer to according to Project Management Institute? A) Project consultant B) Project researcher C) Project manager D) Project procurement E) Project funding mechanism

  6. Soru 6

    6. Which of the following is not listed among the the dures of the projet team markers? A) Sharing their personal agenda and life with other team members "B) Attending and active participation in the meetings C) Providing effort to the whole project to meet ne apjectives D) Delivering expertise Working with users to identify and meet business requirements

  7. Soru 7

    Which of the following is among the internal stakeholders of a project? A) Suppliers B) End users C) Customers D) Sponsor E) Shareholders

  8. Soru 8

    I. Exchange of purpose II. A right to say no III. Joint accountability IV. Extreme dishonesty Which of the above are required to develop the idea of partnership between the project manager and the team? A) lard B) II and C) I, Il and Ill D) I, Ill and E) II, III, and

  9. Soru 9

    9. Which of the followings defines The Project Risk Management Methodology? A) It is the definition of risk probability and impact levels. B) It is the content and format of risk reports. C) It reports the budget, the unexpected situation and the principles. D) It is an explanation of how you plan to implement the project risk management plan. It is an explanation of the roles and responsibilities of the persons performing the activities.

  10. Soru 10

    Which of the following is not among the strategies that can be used to avoid risk? A) ) Removal B) Transferring risk and insurance C) Mitigation D) Acceptance E) Denial

  11. Soru 11

    Which of the following is not a component of SWOT analysis? A) Strengths B) Weaknesses C) Opportunities D) Shareholders E) Threats

  12. Soru 12

    12. Which of the below is used to determine the likelihood of a particular risk occurring in a project? A) Interpersonal and team skill ny By Risk probability and impact assessment Risk data quality assessment D) Expert Judgement E) Risk categorization 1 *

  13. Soru 13

    " is calculated as multiplying workforce by duration." What is the correct term to fill in the blank? A) Person-month B) Man-month C) Man-hour D) Person-hour E) Staff-hour

  14. Soru 14

    What is the evaluating date of a project? A) Mid-control date B) Reporting date C) Status date D) Ongoing evaluation date E) Progress controi date

  15. Soru 15

    , -_ is the difference between the latest finish late of the last activity and the earliest start date or the first activity of a projeci Which of the following, complete the sentence above correctly? A) Project completion time B) Master plan C) Budget D) 1"D) Workload E) Baseline plans *

  16. Soru 16

    There are two basic indicators to evaluate a project in terms of cost and workload. Which the following states the correct indicators? A) Cost Performance Index (CPI) and Staff Performance Index (SPI) B) Cost Performance Index (CPI) and Schedule Performance Index (SPI) C) Creativeness Performance Index (CPI) and Strategy Performance Index (SPI) D) Cost Performance Index (CPI) and Strategy Performance Index (SPI) E) Calculation Performance Index (CPI) and Schedule Performance Index (SPI)

  17. Soru 17

    Which of the following sub-plans is included in the projest management plan, not A) Updates B) Risk C) Procurement D) Scope E) Schedule

  18. Soru 18

    Which of the following is not among the project life cycle? A) Initiating B) Planning C) Executing D) Closing E) Revaluating

  19. Soru 19

    Which of the following can not be said about the Postmortem Review? A) Postmortem examination meetings and final reports begin at the planning stage of the project. B) The actual postmortem work is done one to six months after the project team, the operatión téam or the customer deadline. C) The tools and templates for postmortem work are related to the future, even if they are related to the past. D) It is important that postmortem review meetings focus on people rather than processes. E) The work and workload associated with postmortem activities should be minimal.

  20. Soru 20

    A project closing plan should include the some sectlons. Which of the following is not one of them? A) Executive Summary B) Start Approvai C) Project Closure Deliverables D) Project Scope and Business Objectives E) Project Closure Documentation